InRow SC Operation4
Electrical inspection checklist
The electrical inspection verifies that all electrical connections are secure and correct and that the
cooling unit is properly grounded.
Electrical Hazard: All electrical wiring must comply with local and national codes and
regulations.
Electrical Hazard: The equipment must be grounded (do not use a water-pipe ground).
Mechanical inspection checklist
The mechanical inspection verifies that all mechanical components and connections are secure and tight
and ready for start-up and system charging. The inspection ensures that field piping is properly installed
to promote oil return to the compressor.
Caution: Improperly installed piping may result in improper operation and possible damage
to the cooling unit or surrounding equipment.
Ensure that the:
Incoming voltages match the phase and voltage listed on the nameplate.
Electrical wiring complies with local and national codes and regulations.
Cooling unit is properly grounded.
Electrical connections are tight, including contactors, terminal blocks, controllers, switches, relays,
auxiliary devices, and field connections.
Ensure that the:
Fans are turning freely and that the blades are not distorted or bent.
Condensate drain line is at least the size of the drain connection.
Mechanical connections are tight, including compressor and receiver connections.
Ceiling tile adapter is secured to the building structure with properly-sized safety wire.